Summary

A resident warned the existing Carriage Trails lift station may be near capacity with apartments and hundreds of new homes coming. Staff explained the next lift station is designed, developer-funded (~$1 million), and timed to come online in late 2028/early 2029, with connections capped at 300 homes until then.

At a glance

Total mentions
4
Last 30 days
3

Discussed at 2 meetings in the last 60 days; most recently Oct 28, 2026.