Summary
A ~445-foot road connection joining the two stubbed ends of Charlesgate Road, with curbs, sidewalks, and utilities — construction starts by September and should wrap up by December 2026.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Jul 13, 2026.
Impact analysis
Up to $435,000 from the Capital Improvement Fund.
Neighborhood residents gain a direct connection and better emergency access.
Mentions & discussions (4)
City Council Meeting — July 13, 2026
Council funded two road projects — closing the Charlesgate Road gap and buying right-of-way for the Chambersburg Road Phase IV widening.
Council Work Session — July 7, 2026
A ~445-foot road connection joining the two stubbed ends of Charlesgate Road, with curbs, sidewalks, and utilities — construction starts by September and should wrap up by December 2026.
Council Work Session — May 5, 2026
A new 445-foot road will finally connect the two stubbed ends of Charlesgate Road — a project Ward 2's council member has pushed for years. It costs an estimated $400,000-$500,000 and should be built this summer and fall.
Planning Commission — January 13, 2026
The city dedicated land to connect both sides of Charlesgate Road, linking two neighborhoods. The city will pay for and build the missing road segment.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Huber Heights
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.